Water meter installation

Water meter installation
1, select the correct caliber of the water meter;
2, the level of installation, the surface up, the direction of the arrow on the case with the same direction of water flow. Installation location should avoid exposure, flooding, freezing and pollution, easy disassembly, meter reading. The new pipeline must be in the pipeline of gravel, hemp and other debris washed and then installed water meter, so as to avoid water meter failure;
3, the water meter should be installed upstream and downstream valves, the use should ensure that all open;
4, the upstream and downstream water meter to install the necessary straight pipe or its equivalent rectifier, requiring the length of the upstream straight pipe is not less than 10D, the length of the downstream straight pipe is not less than 5D (D for the water meter nominal diameter). For the eddy current caused by the elbow or centrifugal pump, it is necessary to install the rectifier before the straight pipe section;
5, water meter installation, should pay attention to the lower reaches of the water pipe outlet than the water meter 0.5m above to prevent the water meter due to lack of water within the pipeline caused by measurement is not correct;
6, the water block anti-clogging performance is excellent, but the silt and weeds in the pipeline reflect the sensitive, in the course of the use should be avoided. If there are silt and weeds in the pipeline should be cleaned up in time, otherwise it will affect the normal measurement of water meters.